Due to extremely poor ground conditions, a cost analysis was carried out and it was elected to install a gravel raft.
Excavating over 900m³ and installing a raft system with multiple geotextiles layers and a subsoil drainage system.
Project managed by Constructive and delivered in a team with BMC and Geosolve, the successful builder walked onto a clean, dry, and engineered site.